JAMMU & KASHMIR Ichgam Receiving Station being augmented : Dy CM | KNO Published 329 weeks ago on January 19, 2018 By KashmirNewsObserver Deputy Chief Minister, Dr. Nirmal Singh informed the House that augmentation of Receiving Station from 1x6.3 MVA to 2x6.3 MVA, alongwith other system strengthening works at Ichgam, Budgam has been approved under DDUGJY at a cost of Rs 0.75 crore. He was replying to a question by Aga Syed Ruhullah Mehdi. However he said that the augmentation project was delayed due to litigation. “The tenders for the augmentation project were invited but subsequently cancelled. The re-tendering of the works could not be undertaken owing to ongoing litigation in High Court, Srinagar” Deputy Chief Minister said.(KNO) Up Next Draw of lots held for Hajj 2018; 9773 pilgrims from JK to perform Hajj this year : Veeri | KNO Don't Miss 40000 pension cases to be cleared soon : Sunil Sharma | KNO